Dirt Road to Real Road

Question:
People used to 4-wheel and dump trash on Buffalo between Russell and Oquendo. Now they’re turning it into a real street. What’s the time frame for this?
Jane

Answer:
This was a dirt road for years. Now, any ATV’s are going to be replaced by actual cars.
This section of Buffalo is included in the PM 10 paving project, where various roads in the southwest part of the valley will get paved over.
Construction on this project started October 5th.
Most of the project should be complete by mid-February.
More good news in this area, work is also being done on Durango Drive from 215 south to Hacienda, which is estimated to be finished by late March.
Very good news for your SW valley commute, also making it easier to get to Opportunity Village Center nearby.